Home News Control Point System test 29th April 2015
23 apr 2015

Control Point System test 29th April 2015

BritNed would like to inform you that we are replacing our current Control Point System which is controlling the flows of the BritNed Interconnector.  

As part of the replacement process we are planning a two hour flow test with the new system on 29.04.2015. For the planned flow test we will have to:

  • Limit the offered Intraday Capacity for four hours for Business Day 29.04.2015 to zero MW
  • Limit the offering of additional BritNed owned capacity towards the NWE Market Coupling for four hours on Business Day 29.04.2015 to zero MW
  • Countertrade BritNed’s position in the market for two hours to avoid any imbalances arising on the NL and GB networks

This test will not lead to any Curtailment or imbalances for our Participants. The exact two hour time window in which the test will be executed will be published on 28.04.2015 once known by BritNed.