28 apr 2015

Update Control Point System test 29th April 2015

BritNed would like to inform you that the announced Control Point System flow test which is planned for 29th April 2015 is scheduled between 14:00 and 16:00 CEST.

As already announced following measures have been taken to allow the test to be performed:

  • Offered Intraday Capacity between 13:00 and 17:00 CEST has been set to zero
  • No additional BritNed owned capacity had been offered for the period between 13:00 and 17:00 CEST towards the NWE Market Coupling on Business Day 29.04.2015
  • BritNed countertraded its position in the market for the hours between 14:00 and 16:00 CEST

 

This test will not lead to any Curtailment or imbalances for our Participants.